Hi Experts,

When I am trying to create new BP it is throwing an error message that

" Grouping ZEM has external number assignment, enter a number "

and when i am trying to see the Error information, it is showing that

Grouping ZEM has external number assignment, enter a number

Message no. R1091

Diagnosis

The business partner needs a key to identify it. This key was not specified.

System Response

The system issues an error message.

Procedure

Enter a key in the dialog. If it is a background process or an XML message process, contact your system administrator.

So can any one Explain it what is this Issue?

Thanks,

Krishna.

View Entire Topic

Hi Folks,

I face the same issue, but after trying to reach "BP Grouping", I face Dynpro runtime error.

Any advise?

Many thanks.

former_member34
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi there,

You have a question and need help by the community? Instead of posting into an old question thread, it is more helpful for you, if you create your own question. Here is how to get started:

  1. Learn about asking and answering questions in SAP Community with this tutorial: https://developers.sap.com/tutorials/community-qa.html
  2. Ask your detailed question here: https://answers.sap.com/questions/ask.html
  3. Wait for a response.

That's it. Thank you!

Best regards

Jennifer

Your SAP Community moderator

AllanDB
Explorer

Hi Jennifer,

Had the same recently this is fixed by an SAP note : 327150.

Kind regards,

Allan

roger_reeves1
Participant
0 Kudos

Great that you provided the OSS note Allan - All I needed to do was execute a clean up program (SE38)

BDT_CORR_003.