Corina_Kinzel
Advisor
Advisor
In this blog post I’d like to outline the innovations for SAP S/4HANA Cloud 2208 in the area of Enterprise Portfolio and Project Management. These are the topics that are covered:

 

Watch my video to get a glimpse of the new features:

https://youtu.be/ghXMWbcV4ic

 

Project Stock Enabled for Projects with Revenue  


Already in August 2021, we have enabled project stock for investment projects tightening our procurement integration. With this innovation, project procurement controllers can plan and trigger procurement of stock materials into project stock. By using the demand type ‘Project Stock, Direct Purchasing’, materials are put to stock before they are consumed. When stock materials are kept and managed in stock and the consumption happens at a later point in time, there are no immediate costs. Only after consumption, actual costs will follow immediately which is also documented with a goods issue.

The advantage of project stock compared to plant stock is that the requested materials can only be consumed by the WBS elements and assigned orders to which the project stock belongs. In other words: The materials cannot be consumed by other projects or orders which are not assigned. There is also a provision for separate valuation for project stock. This ultimately helps you in your planning and increases your project-procurement efficiency.

With the SAP S/4HANA Cloud 2208 release, we have further worked on the project-procurement integration and enabled project stock also for projects with revenue. When you create a project and assign the project profile “Project with Revenue”, then it will automatically be enabled with valuated project stock. The material can be procured externally or produced internally based on material configurations and will be held against the project in the inventory.

How does this improve your engineer-to-order process? On the one hand, you gain better visibility into project procurement related planning, and on the other hand, you get immediate access to stock value in financial accounting.

For projects with revenue which have been created before SAP S/4HANA Cloud 2208, project stock will be disabled.

https://sapvideoa35699dc5.hana.ondemand.com/?entry_id=1_3vkamcef

Figure 1: When creating a project with revenue, project stock is automatically enabled.
(back to top)

 

 

Project Demand API for Enterprise Projects


With the latest release, we’re also bringing a new project demand API for enterprise projects. This service enables you to create, read, update, and delete project demands of enterprise projects. By using the communication scenario SAP_COM_0783, you can manage demands with the following categories:​

  • Material – Non-stock material, non-stock material with limit, project stock (direct purchasing)​

  • Service – Service, service with limit​

  • Resource – Direct staffing


The procurement process is initiated upon project demand request. Along with the demands, also the related supply information as well as resource assignments will be processed.

This API allows for an easy access to SAP S/4HANA Cloud project demand data and it’s easy to embed into custom applications.


Figure 2: Manage project demands via API for enterprise projects by using communication scenario SAP_COM_0783. 
(back to top)

 

 

Project Planning Application Enhancements  


This paragraph gives you insights into the latest updates we’ve made to our ‘Project Planning’ application – The heart of the solution when setting up and managing project structures for enterprise projects. To ensure an efficient management of your projects, we’ve worked on the user experience which brings a better overview of project details.

When entering the ‘Project Planning’ application, a split screen will appear with the Gantt chart and the table chart, each taking about 50% of the screen. This will give you a good overview of the project structure as you can consume project details including visualization of project timelines.

As part of our Customer Influence Program, we have talked to customers who provided feedback about this application. As we heard, it can be cumbersome to see e.g. more columns in the table area. Therefore, we have worked on two new buttons which allow you to consume either the Gantt chart or the table chart on full screen. This way, you can better pay attention to the projects information that you need.

In case you want to consume both charts again in one table, you can always come back to the split screen.

https://sapvideoa35699dc5.hana.ondemand.com/?entry_id=1_u3mwfqtb

Figure 3: Make use of three buttons to focus on Gantt chart, table chart, or both in split screen.
(back to top)

 

 

Value Help Type Ahead  


Last but not least, we have enhanced the value help search in our applications. In the past, when you typed in a value in the value help dialog, the type ahead suggestion list did not show exact matches in the first column on top of the list. To improve the user experience, we have worked on the CDS views so that you can see the exact result right at the top of the type ahead list. In the following, you can find out how the matches are shown:

  • Exact matches in the first column in a type ahead suggestion list would always be shown on top.

  • Fuzzy matches in the first column in a type ahead suggestion list are lower ranked than exact matches.

  • Matches and fuzzy matches in other columns in a type ahead suggestion list are even lower ranked.


With these insights, the system supports you while you’re looking for specific values.


Figure 4: The enhanced value help search improves improves user experience.
(back to top)

 

 

Join the SAP Customer Influence Program for SAP S/4HANA Cloud for Enterprise Portfolio and Project Management


Last but not least, I’d like to make a call to action for all our customers and partners.

In mid-2021, we have established the SAP Customer Influence Program for SAP S/4HANA Cloud for Enterprise Portfolio and Project Management.

Join this program if you’d like to submit improvement request, vote on requests, and if you’d like to take part in regular online sessions which are taking place every 4-6 weeks. During those sessions, the submitted requests as well as possible solutions will be discussed. Moreover, you will get insights into planned functionalities.

Don’t miss this chance to provide your feedback and influence the product.

Feel free to reach out to Nadia Razzaq (nadia.razzaq@sap.com) or Heike Wulf (heike.wulf@sap.com) if you’re interested to participate.

Please note that this program is dedicated to our Cloud development. If you have any requests for our on-premise solution, please provide them via our customer connection project by following this link.


Fig. 5: Join the SAP Customer Influence Program for SAP S/4HANA Cloud for Enterprise Portfolio and Project Management to influence the product.

 

 

Watch the Replays of Our SAP S/4HANA Cloud 2208 Early Release Series!


We’ve hosted a series of compelling live sessions from the heart of the SAP S/4HANA Engineering organization. Missed the live sessions? Watch our replays on demand!

Among the replays, you can find a 30-minute replay, a presentation, and demos for Enterprise Portfolio and Project Management as part of the SAP S/4HANA Cloud 2208 release as well as 20 other sessions on diverse topics like Manufacturing, Finance, Professional Services, SAP User Experience, Developer Extensibility and much more. For more information on the SAP S/4HANA Cloud Early Release Series and how to sign up for it, see this link.

 

For more information on SAP S/4HANA Cloud, check out the following links:



  • SAP S/4HANA Cloud release info here

  • Sven Denecken’s SAP S/4HANA Cloud 2208 Release Blog

  • The Link Collection for Enterprise Portfolio and Project Management here

  • Enterprise Portfolio and Project Management Community

  • SAP S/4HANA Cloud 2208 Early Release Series Webinars here

  • Latest SAP S/4HANA Cloud Release Blogs here

  • Product videos on our SAP S/4HANA Cloud and SAP S/4HANA YouTube playlist

  • Inside SAP S/4HANA Podcast here

  • Best practices for SAP S/4HANA Cloud here

  • SAP S/4HANA Cloud Community: here

  • Feature Scope Description here

  • What’s New here

  • Help Portal Product Page here


 

Follow us via @Sap and #S4HANA, or myself via @CorinaReise and LinkedIn

 
11 Comments
srikanth_kuber19
Explorer
0 Kudos
Thanks Corina Kinzel for the updates,

Project Stock Enabled for Projects with Revenue- Is this functionality available in public cloud version as well ?

 

thanks,

Srikanth

 
Corina_Kinzel
Advisor
Advisor
0 Kudos
Hi Srikanth,

thank you for your interest. All the updates in this blog post refer to our public cloud. So yes, all this functionality is available with SAP S/4HANA Cloud 2208.

Best regards,

Corina

 
srikanth_kuber19
Explorer
0 Kudos
Hi Corina,

That's great! Thank you for the quick update

Does that mean deliveries from project will also be enabled ? Currently in public cloud version i  guess deliveries are possible only from sales order item linked to project

 

Thanks

Srikanth
Corina_Kinzel
Advisor
Advisor
0 Kudos
Hi Srikanth,

Deliveries from projects are not planned to be enabled. As you mentioned, deliveries are only possible from sales orders.

Best regards,

Corina
Ulka1
Explorer
0 Kudos
In ECC 5.0 the project stock control was possible using the config , happy to see  it’s default now.
João_Lampreia
Explorer
0 Kudos
Hi Corina

I hope you are well. Regarding Project Demand APP some of my customers would like to have additional field in filters and item lists.  Materials and Material Groups for example are crucial to group and organize project demands . Is there a way to add to the app filter fields that are part of detailed Project demand record?

I say in the roadmap that is planned to release  Project Demand Business Object for customer delelopments but we would like to use and extend fields in the standard APP

Thanks a lot

João Lampreia
0 Kudos
Hi João,

We had shipped the app with a set of fields in the filter based on the customer feedback we had received back then.

In case these fields are needed to enhance the standard app, I would request you to raise this request in Customer Influence Portal. https://influence.sap.com/sap/ino/#/campaign/1858

Regards

Arun.
Hisham
Advisor
Advisor
0 Kudos
Excellent Blog Corina, Thank you for sharing.
Javier_del-Peso
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hi corina.reisenauer
Is it possible still to have the project stock parameter default to non-valuated project stock?

Looks like is not an option anymore but some customers want to have project costs related to direct materials to be recognized before goods are issued and this is not possible with valuated project stock.


Regards,


Javier del Peso
DequanXu
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hi Javier del Peso,

It was decided to go with only valuated project stock before. This project stock parameter is dependent also on Finance functions. Your feedback is taken over by our product management team.

 

Warm regards,

Dequan Xu
Javier_del-Peso
Product and Topic Expert
Product and Topic Expert
0 Kudos
Thank you dequan.xu
Appreciate the feedback.


Regards,


Javier del Peso