on 11-25-2021 11:14 AM
Hello Gurus,
I am facing a problem with delivery header dates in processing tab for the following fields.
- Trans. Planning
- Loading
- Planned PGI
- Delivery date
Our business scenario is to create collective outbound delivery for various order with various dates, system populating old dates (dates in past which is senseless), we need to have dates starting from delivery processing date to future. How to control it.
Please observe the following example;
order 1
- Trans. Planning 4 jan
- Loading - 4 jan
- Planned PGI - 5 jan
- Delivery date - 7 jan
order 2
- Trans. Planning - 5 feb
- Loading - 5 feb
- Planned PGI - 7 feb
- Delivery date - 9 feb
I am creating delivery on March 10, in delivery --> header processing tab dates should show in future;
- Trans. Planning - 15 March
- Loading - 15 March
- Planned PGI - 17 March
- Delivery date - 19 March.
How to control these dates, any help would be highly appreciated.
Regards,
Anand KS
Have a look at OSS note 2346428
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @anand.ks
You could try to reschedule the sales order schedule lines delivery date. As all the other dates mentioned above are calculated based on the delivery date. So if you have a future date in the schedule lines, then the other dates would be also calculated accordingly.
Thanks
Sreemohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks Sreemohan for your reply..
Our delivery always carry numerous lines (say more than 100 lines), each line coming from different sales orders. when created collective delivery for all these lines, delivery header should take latest dates, currently it is taking some past dates which gives no sense.
User | Count |
---|---|
87 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.