Hi Experts ,

How do I get the Latest finish dates in the BAPI CNECP_MAINTAIN for Planning Form .

I Can find it in Cost Lines ,but when I use a Planning Form/Cost Model I cannot see any inputs for Latest Finish Dates

Note: Planning is done at WBS level without networks

Thanks,

Kehkashan A J

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member861327
Discoverer
0 Kudos

Hi,

do you mean this field - LATE_SCHED_FIN_DATE ?

I have other question for you though..

I created a test example for this function module because we need to update this autom. during migration.

However I keep getting the dump "SWITCH_NOT_ACTIVE" - however we do not use networks (planning), we only use WBS elements. How did you get pass this?

Rgds, bert