cancel
Showing results for 
Search instead for 
Did you mean: 

Order has Missing Parts

santosh_kanta3
Participant
0 Kudos

Hi SAP Gurus,

I am facing one problem. the scenario is as follows.

client is having 4 plants. i am doing Production Order for Semi finish material in Plant 2. but Raw material stock material is in Plant 4. i suggested to transfer stock fom plant 4 to plant 2. but client wants this to be done automatically. he don't want to do it everytime. please suggest me what to do.

Regards,

Santosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Assign the SPK 70 (Withdrawal from Alternate plant ) for rawmaterial at Plant2 and set the backflush indicator.

Assign the Issuing plant as Plant4 at SPK settings(SPRO)

I hope this will solve your problem

Pradeep

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

If the scenario stated by you is regular and only the plant 4 is issuing and plant 2 is receiving always. then what our members stated is ok. If this is not constant n u need to reshuffle every time. THE ONLY alternative u have is flexible planning.

Hope this is clear and pl reward

Nanduri

Former Member
0 Kudos

Hi Santhosh,

You can use special procurement key create reservation in alternate plant. By maintaining the special procurement key for the semifinish material in material master MRP 2 view you can automate this process in MRP.

Regards,

Srini

Former Member
0 Kudos

Please check your MRP settings... are you looking at multi plant level MRP?