Hello All,

Plant Specific material status xx whicn i have created to block procurement, MRP, production.

I thought sales order activity is not in scope of plant status.

but i observe,when material having plant status xx in Plant Specific material status field in material master, then i can create sales order, but when i use va02 to change sales order it is blocking due to xx plant status. For ex. if i change delivery date in sales order.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member183424
Active Contributor
0 Kudos

Assigning blocked status in purchasing view will not impact SO creation process. There is separate blocking function available in Sales view for blocking SO process. See this existing thread https://answers.sap.com/questions/4040723/prevent-sales-order-for-blocked-material.html

Please check comment from Lakshmi.

jignesh_mehta3
Active Contributor
0 Kudos

Hello,

What is the Valid from Date (of Plant Sp. Material Status) in Material Master?

Further please check the Material Master for "X-distr.chain status" and "DChain-spec. status" feilds under Sales Org 1 screen of Material Master.

Its possible a relevant status under Sales Orgn 1 is generating this error message.

Thanks,

former_member833285
Discoverer
0 Kudos

Thanks Jignesh!

Valid from Date (of Plant Sp. Material Status) is blank.