Problem in Creating PIR in MD61

santosh_kanta3
Participant
0 Kudos

HI SAP Gurus,

I am getting a error while creating PIR's in MD61.

The input is Req. plan Number, Plant, Version, Planning Horizon: From-01.12.2008 to 02.01.2010

SAP system is not allowing to create or copy PIRu2019s for December-2008. Following is the message:-

u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.

what must be the problem?

Please Help.

Thanks & Regards,

Santosh

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello Santosh

it cause your replenishiment date is out of your factory calendar.

there has same resolution, but the best solution is maitian your factory calendar to 2020 or more.

Kim

santosh_kanta3
Participant
0 Kudos

Hi kim,

But when i change my Planning Horizon in the 'To' to just 2 days, then the system is not showing any error. or even when i change the Planning period from 'W' to 'D'. there is no error. in fact the error is only for 'W' not for others.

what must be the problem.

Thanks & Regards,

Santosh

Former Member
0 Kudos

Hello Santosh

the caculate logic is

Current date + Planning horizon(work day) + rescheduling date(work day) + 1 Week(if you set lot-size is "WB" in Material master)

currently the result is out of the during factory calendar.

yes you can maintain the planing horizon to more small or change the lot-size from "W" to "D"

it can resolve temporarily, but with the passage of time will occurs again.

so i think the best resolution is maintain the factory calendar to more big.

thanks

kim

Former Member
0 Kudos

Hi,

Either change the Planning horizon dates manually in the initial screen on MD61 or use T-code OMPD - Assign default values & presettings in PIR and change the value in the Planning horizon field.

Now the dates wil lie within the factory calendor.

Try this..

-Thaila Shree

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Check Valid to date of your Factory Calendar.T.code is SCAL.

Regards,

Dhaval

santosh_kanta3
Participant
0 Kudos

Hi Dhaval,

Thanks for ur reply. I checked my Factory Calender, it is 2010. but my input is 01.12.2008 to 02.01.2010. then why the system is throwing that error?

please reply.

Thanks & Regards,

Santosh

dhaval_choksi3
Active Contributor
0 Kudos

Hi Santosh,

Check Planing Horizon in Initial screen of MD61.

Regards,

Dhaval

santosh_kanta3
Participant
0 Kudos

Hi Dhaval Choksi,

My Planning Horizon is from 01.12.2008 to 02.01.2010. when we enter this the system is throwing a error saying that u201C02.01.2011 date comes after end of valid factory calendar(Please correct)u201D.

but when i change the Planning Horizon as from 01.12.2008 to 04.01.2008, then there is no error.

why this is happening?

Thanks & Regards,

Santosh

pravin_kusumbe2
Participant
0 Kudos

Please check the planning table in MD25

santosh_kanta3
Participant
0 Kudos

Hi Pravin.

thankd for ur reply. there is no planning calendar maintained.

Thanks & Regards,

Santosh Kanta

santosh_kanta3
Participant
0 Kudos

Hi

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Extende the holiday calender before extending the factory calender then cheack.

Regards,

R.Brahmankar