Hi Expertise,
We have one issues while run the standard cost estimate CK11N, getting small differences against activity type,
we have maintain the price in KP26 Rs.3.17, in Routing we have maintained conversion
31,109 KG = 10000 EACH, we are calculating in KG. 1 KG = 1,so 31109*3.17 = 634260.30, But in CK11N Showing Rs.634000.00 (In Round) here the differences 260.30. where we need to change the configuration.
Please let me know.
Thanks
Pranav
hi,
In CK11N/CK13N, you can see the cost calculation for the single unit. based on that you can change the activity rate in KP26.