Dear experts,

in COR3 I can jump into the cost analysis after process odder has been confirmed and vairances have been calculated.

But this is only working for one process oder. Is there any SAP standard report or TCode where I can enter a material, plant or multiple process orders to see the cost analysis of the entered process orders / materials?

This would be very beneficial instead of going into each process order.

Many thanks in advnace.

Best regads

Patrick

View Entire Topic

Hi Please try if S_ALR_87013127 is suitable for your requirement

patrick_g1
Active Participant
0 Kudos

Many thanks. This seems to be excactly what I was looking for 🙂