on 04-27-2023 9:26 PM
I have a requirement, wherein the client has a third party system (NOT SAP) doing the MRP run, after MRP run the third party system sends purchase requisitions created, to S4. These purchase requisitions are then to be directly converted to scheduling agreements or schedule lines. The problem that I have are
1- How to create Scheduling agreement directly from purchase requisition
2- If we will be able to create the scheduling agreement automatically, then how can every subsequent purchase requisition will create scheduling lines referring to the created scheduling agreement.
3- When the scheduling agreement gets consumed, how will the system then create a new scheduling agreement automatically and then follow the cycle.
Client doesn't want to create scheduling lines directly from purchase requisitions from MRP run.
Is there a way by which we can do configuration in the system to achieve this scenario?