on 01-05-2023 7:04 AM
I am using flexible planning, In that i have selected characteristic as Plant, material group, & material.
In planning hierarchy as given the proportion to material of that material group.
Now, when i am transferring the planning data to demand management (T-code: MC90).
I am able to select material only (this means, I will have to transfer data for each material in that material group).
Is there any provision for transferring data at material group level.
Hello hitman45
I think flexible planning mass processing should do the job - SAP Help How to Transfer Data to Demand Management with Mass Processing
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.