Hi All!

We have 5 Plants: 4 commercial plants and 1 production plant.

The sales orders are created in the commercial plants with a Make-to-order with consumption Requirements type; (Individual customer stock is an issue of the client).

Planned independent requirements are entered at finished product level with Consumption indicator for planning requirements 4 - Flexible Consumption for Different MRP Elements (BAdI); we create the purchase order (L - Subcontracting) for the finished product based on the PIR.

We need to do the consumption and reduction of planned independent requirements based on the purchase orders creation or in the Goods Receipt for the Outbound Delivery.

We implemented the BAdI MD_PIR_FLEX_CONS but the BAdI isnu2019t trigger for Planning strategy 10 or 40 but. The BAdi is trigger only when Requirements class of the Requirements type of independent requirements as value 2 (Consume planning w/o assembly) in the Consumption indicator and value 3 (Single-item planning) in the Planning Indicator.

How can we trigger the BAdI in a MTS strategy u2013 The BAdI documentation doesnu2019t mention that can only be used in MTO strategy?

Thanks.

Regards.

Adelino

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Adelino

Strategy 10 is a special business case without consumption and only with the PIR reduction during the delivery (goods issue). You can see in customizing OPPS that both requirements KSL and LFS are set with "No consumption with customer requirements". In this case, BAdI MD_PIR_FLEX_CONS is not called.

The BAdI can be used with strategy 40, so please make sure that the consumption indicator of the PIR is set to '4 - Flexible Consumption for Different MRP Elements (BAdI)'.

BR