Hi Experts,
we have a requirement.. there are 2 sloc managed by the same plant but they are located at some distance.
all materials are stored at the central sloc.. but prod takes place at the other location..
we are planning to use MF60 to stage material againsta process order.. the system is creating mat doc/delivery agsint this MF60 from the issuing sloc but.. we cannot link the process order with the delivery document
delivery is created because the sloc is HU managed
We need to link the process order with the delivery document. Our preference would be to store the process order in one of the free fields of the delivery document.
Any suggestions or alternative solutions.....
Best Regards
Roy
Dear generate pull list against production orders in MF60 which will automatically links and in supplying location give the other
location (delivey point).
Cheers
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
9 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.