Lot Size in MTO?

Former Member
0 Kudos

Hello SAP friends.

I have a little problem with MTO, strategy 20 and Fix Lot Size.

Scenario:

My client receive a a sales order for on FG quantity 10 UN. MRP run and system proposes 1 PldOrd quantity 10 UN for the requirement (Sales Order).

My client don't produce the 10 UN because the production process is very complicated so he's going to produce 1 at time.

My question:

How can I use Fixed Lot Size with MTO strategy 20 in SAP? Is there any possibility that system creates 10 PldOrd quantity 1 UN for the sales order quantity 10 UN?

Thanks in advance,

Adelmo Silva

-


View Entire Topic
zlcalero
Explorer
0 Kudos

Hi, please check in TX OMD7 or OMDY, the quantity in MAX.PUR.ORD.PR.(max ord ord propose). Change or leave blank that field and test MD02.

Change Material (mm02) in MRP FX , and fixed lot size 1

Regards

ZCalero