on 04-27-2011 12:29 PM
Dear PP experts,
Is it possible to split the PIR of all the materials for which LSF is entered in MD61?
We have already entered the plan of around 50 FG materials in MD61 on monthly basis. Now we want to split the plan of all these materials into weekly basis.
I know the option in MD61 / MD62 wherein we can distribute the plan into weekly basis. But I could do it only for 1 material at a time. Is it possible to do the same for all the materials at one time?
Is there any configuration to be done for this?
Pl. suggest.
Regards,
Prashant
you can try in MD67, if you have already period split in week in your system then proceed executing , other wise
create a automatic splitting in OMPH mentioning NO of weeks and save
and then try to execute in MD67 with created period split by maintaining the list of material
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sundaresan . E. V ,
Thanks for the reply. I tried the way you suggested, but the PIR didnot split. Is there any more config setting or master setting which I am missing? Also pl. let me know the splitting takes place as per the quantities mentioned in the Plan or as per the batch size of the material.
For e.g for one material if the quantity planned is for 10 batches and for the other material ther is only one batch planned, then in such case how shall be the behaviour of the system for splitting the PIR?
Pl. revert back.
Regards,
Prashant
Dear Prashant,
You must make sure that the following three steps have been carried out before you can automatically split the independent requirements:
Regards,
Adelino Pereira
User | Count |
---|---|
95 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.