Hi,

Greetings,

1)I have maintianed Inactive PIR for Periods P1 -10 P2 -20 and P3-30,

2) I expect BOM to be exploded in same ratio and give component demand.

3) But for one period i get this error - Outside of simulation and not able to change source of suppy or Pull in quantity.

this is affecting the component requirements.

Any suggestions.

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Check the reference dates when creating the simulation, in order to ensure that all the demands and the replenishment elements are within the reference dates.

Regards,
Caetano

Dsk
Active Contributor
0 Kudos

Hi Greetings,

1. My Demands are in Months and like below in the MD63

M1-Jan 2024-10

M2-Feb2024-20

M3-Mar2024-30

2. During the scenario creation i have created from 01012024 to 01052024

3. in the results some qty is not coming correctly - Kindly find the highlight

Any suggestions.