Production order issue

Former Member
0 Kudos

Hi Experts,

I am not able carry out MIGO after a change in the material master.

In production order, while trying to do read pp master data -

system giving error "system status PCNF is active"

Please explain.

Thanks in advance.

Regards,

Suresh.

View Entire Topic
Former Member
0 Kudos

Dear Suresh,

Which goods movement are you trying do- 261 or 101?

What changes have you done in material master?

Former Member
0 Kudos

Dear Shaunak,

I changed the valuation class in material master and trying to do MIGO.

Regards,

Suresh.

SaniketK
Participant
0 Kudos

Hi Suresh,

We can update the changes in order in only ord. release status.

You have to cancel the order confirmation first in CO13 and then you can do the read PP master data.

Thanks,

Saniket