Production subcontracting leadtime

0 Kudos

Hi experts,

We have an issue regarding the production subcontracting flow at our customer.

Routing, bom, production version are all maintained. Also an inforecord is created.
But when the PR is generated it doesnt respect the leadtime of the inforecord even though it does find the inforecord. Any idea why this is happening?

The delivery date in the PR/PO is the start of the manufacturing order for some reason.
But the delivery date should respect the leadtime of 2 weeks as mentioned in the inforecord.

Purchase inforecord and delivery date are visible in the operations of the production order.

View Entire Topic
Patrickcapg2023
Explorer
0 Kudos

Hi

Have you check control key at operation in routing that release this PR ? . You can should between lead time at operation (Standard value time) or external procurement(PIR planned del time)

BR

Patrick

0 Kudos

Control key YBP2 is used. But everything looks okay there.