Hi Expert,

We're doing ECC conversion to HANA.

Regarding PP area, as there is storage loaction MRP was used in ECC,
so I activated MRP area and created new MRP area for storage location.
after ran the report MRP_AREA_STORAGE_LOC_MIGRATION,
there has been no error.

The question is :
At the moment storage location MRP is still in material mater MRP4 view
and I haven't set MRP area in MRP1 view.
should I set MRP area manually in MRP1 view for all materail mater?
Or it will be updated automatically after conversion?
If I should set manually how do I get the list of material mater as there has been no error in MRP_AREA_STORAGE_LOC_MIGRATION, I cannot know which one was affected

View Entire Topic
Prasath
Contributor
0 Kudos

Hello Chao, If material needs to be excluded or included from MRP below fields must be set automatically if it exists with MRP area in material master. I hope MRP would have been created during data migration ECC to S/4.

Excluded from MRP will be carrying ND MRP type and other will carry PD as regular.

MARD MRP 1.jpg

 

 

 

 

Regards,

Prasath