Dear Expert,
I am having problem with Resource Load. When I tried to execute "Run Load Leveling", it appeared two messages "No operations relevant to load leveling found" and "Not possible to schedule any operations for selected resource". What am I missing? Kindly advice
Thanks and Regards,
Tandy
Dears,
If you want to use the load leveling, the production proposal should not be in status : Firm. Otherwise, as for Supply planning, date could not be change.
Only production proposal "free" could be changed by the load leveling.