Dear Gurus ,

How is it possible to make the shipment cost and freight settlement cost part of the material valuation in SAP LE and SAP TM ?

Accepted Solutions (0)

Answers (2)

Answers (2)

Garcia
Advisor
Advisor
0 Kudos

Hi sameer.j2 ,

Years ago we did it with a custom process/report, there was no standard solution available.

It was quite tricky since the freight settlement might come in when the warehouse stock levels are already low... it had a big impact in MAP values.

All the best,

Neeraj_Jain
Active Contributor
0 Kudos

Hello sameer.j2,

Please refer below SAP thread. Hope it's clarifies your query.

https://answers.sap.com/questions/9036249/post-sto-shipment-cost-in-to-material-cost.html

Regards,

Neeraj Jain