WBS restructuring

ADILSONBENNY
Participant
0 Kudos

Dear Experts,

I did some project restructuring via programs RKANBU01, RKANBU04, and tcodes CJEN, CJBN but I could only do this for only one object at a time. Is it possible to do this same mass process somehow?

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

Caro Sr. Sobral,

Please try to use * for the Project field.

Thank you,

Paulo

ADILSONBENNY
Participant
0 Kudos

Dear Paul,

Thanks for the reply but, my attempt to return a Dump.

Is there any way you can do this? maybe ranges by range?

Regards,

Adilson

Paulo_Vitoriano
Active Contributor
0 Kudos

You can use ranges to reduce the data selection at a single execution. But I would also suggest to address the issue with the lack of memory available for processing.

Answers (2)

Answers (2)

ADILSONBENNY
Participant
0 Kudos

Dear Paulo,

Thanks for your Answers!

Regards,

Adilson

ADILSONBENNY
Participant
0 Kudos

Dump in my try...

Paulo_Vitoriano
Active Contributor

You can work in parallel in two directions. 1. Address with the Basis team the issue for the lack of memory.

2. You can use intervals or you can even paste the list of projects to the extended selection if you have specific project ids.