Anyone heard more on Updated : VSaaS Patch Release for Sandbox, Preview and Production Environment for this week?

AF21
Galactic 2
Galactic 2
0 Kudos

We got the email last night: Updated : VSaaS Patch Release for Sandbox, Preview and Production Environment

With the short time window we are not sure what to regression test and we are looking to see how others are handling these fixes. Does anyone know if connectors or jobs or system access will be impacted. I know the message was vague so we are trying to guage the impacts. 

1 ACCEPTED SOLUTION

Hi Everyone, the following issues are part of 1808p21 getting deployed this week:

4 REPLIES 4

may_thang
Galactic 6
Galactic 6
I went to the following link to look up the patch information since the email didn't provide any details:

https://help.sap.com/viewer/e29bd9411c0d42ec9073f4d5983fd1b7/1808/en-US/83b0f03f02ee472196468fb38894...

There are 2 fixes for 1808 p21, user curriculum page error fix and curriculum item status report. I'm still waiting on confirmation from our CSM. I was hoping Sany would post on our community board to let us know.

Hi Everyone, the following issues are part of 1808p21 getting deployed this week:

0 Kudos
Hi Sany, we are seeing an issue in Production where if a user has a large number of curricula assigned (over 70 approx.) that it takes 40 secs for the full curricula to display on the user snapshot. Have you seen this at other companies - we have logged an incident and the helpdesk responded to say this was a bug and a patch was being worked on but we don't have any idea at this stage as to when the patch will be deployed for validated customers - are you aware of this issue? - I'll post a general question to the LSIG to see in another post.
Regards
Stuart

Maria_Molvin
Galactic 4
Galactic 4
0 Kudos

I posted this on another thread - the link in the emails is not working, at least for me, to the release notes. We need these to do understand the changes and to do a change control in the next day.