Hi, SNP Experts,

Production order open status in ECC are not showing as production confirmed in APO Planning Book

there is changes in the material setting, is this impact on production order?

I tried to run RIMOGINI but not resolved pls help.....

Thanks in advance 

Joshua H

Accepted Solutions (1)

Accepted Solutions (1)

vijaysap
Explorer
0 Kudos

Hi

I run RIMOGINI for master data change, now production oreders are vissible in planning book.