on 10-25-2018 7:27 AM
Dear all,
When the inbound delivery is created (in EWM) from the inbound delivery notification, the quality inspection is planned and in relevant cases the quality inspection document is created.
The inbound delivery notification is created automatically via the interface and it is automatically activated which results in the automatic creation of the inbound delivery. Thus the inspection planning takes also automatically place.
I am wondering if there's an easy way to somehow debug the inspection planning (or generally the activation of the inbound delivery) - I have been checking if there's a useful (how-to or consulting) OSS note but I was not able to find any. Does anyone know how to do it?
Thanks,
Csaba
Please check the PPF at IDN which gets auto triggered and restults in ID creation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.