Resource is already used by another FO in same time frame

AjayV
Explorer
0 Kudos

I am facing an issue where system is showing error on delivery proposal creation from Freight Order, as below:

Resource is already used by another FO in same time frame

When I checked that another FO, through the planned departure date and time is same, actual is different.

Anyone can help on this?

S0017638052
Explorer
0 Kudos

Have you check the availability of the resource? Ensure that there are enough available resources for that specific one(unlimited resources flag on resource level might be an option also).

View Entire Topic
Neeraj_Jain
Active Contributor
0 Kudos

Hello ajayvohra,

Please refer second answer of below SAP thread if it's works for you.

https://answers.sap.com/questions/11357501/time-conflict-in-freight-order-for-std-process-615.html

Regards,

Neeraj Jain

AjayV
Explorer
0 Kudos

No, it does not work, as that option is already made to no determination.