SAP IBP Calculating current week and aggregating it to next wekk

snlak
Discoverer
0 Kudos

WE have a requirement were in the current week to be displayed as 0 and next week as 1 and second week as 2 and so on

How do we achieve this in SAP IBP through key figure

View Entire Topic
piyush_parekh
Active Contributor
0 Kudos

Hi Sravanthi,

You can also try below

Define a key figure KF1 as : if periodid = current period id then 0 else 1 (give input as any stored key figure same as that of base planning level of this KF1) and another key figure KF2 as : IBP_CAGGR ( KF1, SUM, FORWARD, CURRENT FUTURE) KF2 should reflect what you're looking for.

Please refer the correct syntax from IBP model configuration guide.

Regards,

Piyush