When we are doing urgent transports in ChaRM, at the end of the transport "Request is ready for import again" in both enviroments (QA and PRO)
Is there any way to quit this option and to finish the transport with the action "Request already imported"?
Thank you in advanced
Hello Jolapena,
Please consider the use of variant SAP1: Deletion of import buffer strategy, see details in SAP HELP portal Task List variant
Hope this helps,
Dolores
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Dolores,
Than you for your reply
I have changed the variant as you told me
Now we have the following behavior in the Emergency Changes:
- The transport to Quality System is OK with only one transport
- The transport to Production System still continue with both transports (request is ready to transport again)
Do you now why is the reason for it?
Thank you in advanced
Kind Regards