on 02-28-2023 9:18 AM
Please could you advise how to link multiple diagrams to a process in Signavio Process Manager. Currently I am able to link only one.
Dear Athar,
Many thanks for your request. I would recommend using a custom attribute for that. In this case for BPMN 2.0 on process level. The Data Type should be Diagram link and please make sure to tick the box As List.
After that you can add multiple diagram links to your process via the attributes panel in the editor.
Please let me know if you need further information.
Best regards,
Martin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.