Purpose


This document would be useful for beginners who usually post new thread regarding table links. Sometimes we did not able to recall relation between different tables during New Requirement either we have worked before or not.



Information


Plan Cost:


(1) Manual Cost Planning (WBS Elements):


Pass WBS as into PRPS-PSPNR and obtain the PRPS-OBJNR.


Pass PRPS-OBJNR to RPSCO-OBJNR where value type would be RPSCO-WRTTP = 1 and get Plan cost by adding the value of RPSCO table WLP00, WLP01,...to.... WLP16.


(2) Network Costing:


if we does not have network number than Pass WBS number (PRPS-POSID) to AUFK-PSPEL and get AUFK-AUFNR.


Pass the network number to AFKO-AUFNR and obtain AFKO-AUFPL.


Pass AFKO-AUFPL to AFVC-AUFPL and obtain AFVC-OBJNR (object number for Network Activity).


pass AFVC-OBJNR to RPSCO-OBJNR where value type RPSCO-WRTTP = 1 and get Plan cost by adding the valueof RPSCO table WLP00, WLP01,...to.... WLP16


(3) Actual Cost: if you need actual cost from RPSCO table than you should choose WRTTP=4 rest whole logic would be same in above.


other optional table: COEP-CO Object: Line Items (by Period), this table is also useful when we want to create a custom report line item wise or according to Date/period/fiscal year.


Pass OBJNR to COEP-OBJNR and fetch COEP-BELNR, WTGBTR where COEP-WRTTP=4 and VRGNG NE KOAO.


if you need value according to date range


Pass COEP-BELNR to COBK-BELNR fetch COBK-BUDAT


Compare COBK-BUDAT to selection parameter date and select records on or before selection parameter.


If BUDAT is equal or less than selection parameter date which is 01.01.2015 then select this entry.

Compare COBK-BELNR to COEP-BELNR and obtain COEP-WTGBTR

Budget:


Budget Type:


1. Annual Budget


2. Overall Budget


This is defined in budget profile:


   -Only annual budget.
-Overall Budget.
-Annual + Overall Budget


BPJA: this table is for Budget Annual: For this we have pass PRPS-OBJNR to BPJA-OBJNR and fetch BPGE-WTJHR.
BPGE: This table is for Budget Overall: For this we have pass PRPS-OBJNR to BPGE-OBJNR and fetch BPGE-WLGES.


 


In above table we can have link between PRPS and above two tables. we need to pass OBJNR of WBS to BPEG & BPJA table to fetch values.


Status: SAP hase different types of Status as below:


1. System Status: which is SAP Standard Status, User can not interfere with SAP System Status. according to transaction system status would be activated. Example: CRTD, REL, CNF, TECO & CLSD etc


2. User Status: this is a User defined status which user himself creates and use as per business function/process.


Tables:


JEST-Object Status


JCDO-Change Documents for Status Object (Table JSTO)


TJ02-System Status


TJ02T- text for system status


JSTO-Status Object Info


JCDS-change Document for system and user status


TJ30-User Status


TJ30T-Text for user status


Logic to get User Status of Activity:

Pass the network number to AFKO-AUFNR and obtain AFKO-AUFPL.

Pass AFKO-AUFPL to AFVC-AUFPL and obtain AFVC-OBJNR (object number for Network Activity). where VORNR  is equal to activity number.

then Pass AFVC-OBJNR  to JCDS and get status starting with E* where status inactive= blank
Now Pass AFVC-OBJNR to JSTO OBJNR and get STSMA
Pass STSMA  and Status with E* to TJ30T and get TXT04.

if we need status for any object than we should have OBJNR for required object for Example: if we need to fetch status of WBS than Pass PRPS-OBJNR to JEST-OBJNR. this will return like I0001 or I0002 etc which are internal naming but if you want to see text than you should pass I0002 to TJ02T than you will get status as below:



Commitment:


Commitment is a value which are liabilities arising from contractual obligations incurred on time to time basis. i projects we need to estimate our cost/investment.


to get values forcommitment we should use below link:


Table COOI-Commitments Management: Line Items


Pass OBJNR of PS object in COOI-OBJNR to get values


other option is Pass OBJNR to RPSCO table and fetch values basis of RPSCO-WRTTP = 21,22,23,24.


Integration with HR:


In SAP we have major integration between PS and HR.


we need to check table:


CATSDB - CATS: Database Table for Time Sheet


this table contain all data posted to HR like time sheet whether this is approved or not.


Pass WBS/Network to fetch time sheet posted by Personnel Number.


CATSPS- Cross-Application Time Sheet (CATS): Transfer to PS


This table contain all timesheet which are posted and transfer to PS object.


Pass Network in CATSPS-RNPLNR and get personnel Number and Hours posted Etc.


 


CATSCO-Cross-Application Time Sheet (CATS): Transfer to CO


This table contain all timesheet which are transferred to CO Object.


Pass WBS to CATSCO-RPROJ and get personnel Number and Hours posted Etc.


CATSHR-Cross-Application Time Sheet (CATS): Transfer to HR


This table contain all timesheet which are transferred to HR Object.


Pass WBS to CATSHR-RPROJEXT and get personnel Number and Hours posted Etc.


PA0001-HR Master Record: Infotype 0001 (Org. Assignment)


Pass Personnel Number in PA0001-PERNR and get all details of Personnel Number.


PA0027-HR Master Record: Infotype 0027 (Cost Distribution)


Pass Personnel Number or WBS to get cost distribution list.


Integration with MM:


for integration with MM we can refer tables like: EKKN-Account Assignment in Purchasing Document.


EKKN- Account Assignment in Purchasing Document


we can pass WBS element to EKKN-PS_PSP_PNR and Network to EKKN-NPLNR to fetch PO related to PS object.


EKPO -Purchasing Document Item


we can fetch PO related to Account assignment P, N and Q. for this Pass Account Assignment to EKPO-KNTTP and get PO Number (EBELN). we can also fetch Service PO via Entering item category in EKPO-PSTYP.


EBAN - Purchase Requisition


This table is linked with EBKN (Account Assigned PR), and EBKN is linked with all account assigned Objects for example: WBS Element, Network, Plan no.f.oper., To order, Cost Object etc.


RESB: Reservation/dependent requirements


if any reservation is created for any object than you will get from this table like:


Pass WBS Element (RESB-PSPEL) and get Reservation number.


RKPF : Document Header: Reservation


this table contain data related to reservation. linked to AFKO table via RSNUM


there are many more tables like:


EVPOC:-Percentage of completion:


Pass PRPS-OBJNR to EVPOC-OBJNR to fetch Plan or Actual POC


COBRA-Settlement Rule for Order Settlement


PRPS-OBJNR=COBRA-OBJNR


COBRB-Distribution Rules Settlement Rule Order Settlement


PRPS-OBJNR=COBRB-OBJNR


 


COSB-CO Object: Total Variances/Results Analyses


Pass OBJNR and get result analysis data for Object


PRTP-Sub Projects


PRPS-SUBPR = PRTP-SUBPR


PRHIS-Standard Project Hierarchy


this table is used to identify all hierarchy for a selected Standard WBS


Pass Standard WBS to PRHIS-POSNR and check which is Project ID and Immediate lower WBS and Left and right WBS if available.


PRPSS- Standard WBS Element (WBS element) - Master Data


Pass Standard WBS to PRPSS-POSID and get all master data assigned to Standard WBS.


PROJS-Standard Project ID


Pass Standard ProjectID to PROJS-POSID and get all master data assigned to Standard Project.


PLPO- Standard Network Activity


Pass Standard WBS to PLPO-PSPNR to fetch all activity assigned to WBS


MLST- Milestones


if you have WBS, than Pass WBS to MLST-PSPNR and fetch Milestone assigned to WBS


if you have network than you need to fetch plan no of operation and counter, pass these to MLST-AUFPL and MLST-APLZL and fetch MLST-MLST_ZAEHL (Milestone number), MLSTN (Usage) etc.


SMLS-Standard Milestones


standard milestone are attached to PS objects like standard network.


PRTX-WBS PS Text


Pass WBS to PRTX-PRPSPNR to fetch PRTX-PRTXTKY then Pass PRTX-PRTXTKY to PSTX-PSTXTKY and get PSTX-PSTXTTI (Description).


PRST-WBS BOM Link


Pass WBS to PRST-PSPNR to get Material (MATNR).


QBEW-Project Stock valuation


Pass Material  (QSEW-MATNR) and WBS (QBEW-PSPNR) and get stock and values


MSPR-Project Stock


Pass WBS in MSPR-PSPNR and get Material (MSPR-MATNR) with quantity.


AFRU-Confirmation


Pass AFRU-AUFNR and AFRU-APLFL to get confirmation details


COSS- Cost total for internal posting


Pass Object Number of PS Object and get all values.


COSP-Cost total for External Postings.


FMZUOB-Allocation of CO Object to FM Account Assignment


VBAK-Sales Document: Header Data


Pass WBS in VBAK-PS_PSP_PNR to get details for sales order


VMPA-Selection Methods for Search Help VMPA


When business process is link assembly Process and RRB so we need to check link between Sales Document with WBS.


Pass WBS to VMPA-PS_PSP_PNR to get Sales Order Item or vice versa.


COAS- Details for order against WBSE


This is used to find orders created where WBS as Account assignment.


Pass WBS to WBS of COAS(COAS-PSPEL) to get Order and order type.


 


Resource Related Billing tables:


 


AD01DLI: Dynamic items (DI)


Pass Object number and find all details related to RRB


AD01DLISF: DI Flow: Totals Flow


pass DLINR from AD01DLI table


AD01DLIEF: DI flow: Individual flow


Pass DLINR from AD01LIEF table


Fund Management and Project System:


FMDERIVE006-Derivation rule:WBS Element/CE to Commitment Item/Funds Ctr/


This is used to extract Derivation Rules where WBS/Cost Element linked to Commitment Item/Fund Center


FMDERIVE007-Derivation rule:WBS Element to Commitment Item/Funds Ctr/Fun


This is used to extract Derivation Rules where WBS linked to Commitment Item/Fund Center


Thank you for reading and hope you liked it. I will be regularly updating this Document for rest of important formula/links.


Thank you for your time and feedback!


Suggestions would be appreciated and always welcome to improve Quality of this document.


Warm Regards


Sunil Yadav



45 Comments
mirakbar_ali
Explorer
0 Kudos

Thanks Sunil for sharing, very useful document.

Regards

Akbar

sunil_yadav2
Active Contributor
0 Kudos

Thanks Ali for encouraging me and for like :smile:

Former Member
0 Kudos

Hi Sunil ,

This good for refreshing our knowledge and useful for beginner

Regards

Deepak

former_member218251
Active Participant
0 Kudos

I did not see this document, but I just completed a document around the tables involved in resource related billing. Perhaps we can incorporate this in this document?

Resource related billing data flow

sunil_yadav2
Active Contributor
0 Kudos

Hi Hofman,

Sure i will update this document including your tables too and much more table links :smile:

thanks

Sunil

sunil_yadav2
Active Contributor
0 Kudos

Thanks Deepak :smile:

sunil_yadav2
Active Contributor
0 Kudos

Hi,

I am not able to see your post :sad:

former_member225123
Participant
0 Kudos

Thanks Sunil for sharing a good piece of information with us regarding table links . :smile:

sunil_yadav2
Active Contributor
0 Kudos

Thanks Gaurav :smile:

Former Member
0 Kudos

Thanks, Good information & useful document

sunil_yadav2
Active Contributor
0 Kudos

Thanks Prasath :smile:

former_member218251
Active Participant
0 Kudos

Hi Sunil

Sorry for the late response, was away from the office. It was removed, will send you a message with the tables.

Former Member
0 Kudos

Good & Useful document Sunil ! Appreciate it ! Thanks for your valuable time to document the details.

sunil_yadav2
Active Contributor
0 Kudos

Thanks Aoron :smile:

Former Member
0 Kudos

Thanks

Really Useful information

sunil_yadav2
Active Contributor
0 Kudos

Thanks Omkar

former_member218047
Participant
0 Kudos

Very good information regarding Project related tables. Keep it up. Expecting some more useful information from you.

sunil_yadav2
Active Contributor
0 Kudos

Thanks Sesha :smile:

Will try to post some more useful content.

Former Member
0 Kudos

one place for all sap ps related data origin

sunil_yadav2
Active Contributor
0 Kudos

Thanks Naseer :smile:

0 Kudos

Its a Nice document Sir.

sunil_yadav2
Active Contributor
0 Kudos

Thanks Saurabh :smile:

Shubham1
Employee
Employee
0 Kudos

very well drafted..good

former_member183349
Active Participant
0 Kudos

its really helpful document.

sunil_yadav2
Active Contributor
0 Kudos

Thanks Shubham

sunil_yadav2
Active Contributor
0 Kudos

Thanks Vivek

Former Member
0 Kudos

Hi Sunil,

Just Giving you one Suggestion, Pls add COAS table Details for order against WBSE.

this table helps to find Orders raised using WBS as account assignment.

Regards,

Omkar Deshpande

sunil_yadav2
Active Contributor
0 Kudos

Hi Omkar,

thanks for your Suggestion. will update for COAS table with related details.

thanks a lot

Sunil

Former Member
0 Kudos

Its a helpful document can you also post ps integration with controlling

sunil_yadav2
Active Contributor
0 Kudos

Hi Ataul,

thanks for your remarks. will try to update this documents for CO-PS integration.

jskishore
Explorer
0 Kudos

Hi Sunil,

Thanks, it was really helpful and very good document.

Thanks

kishore

sunil_yadav2
Active Contributor
0 Kudos

Thanks Kishore

srinivasan_desingh
Active Participant
0 Kudos

http://scn.sap.com/docs/DOC-55692

Hi,

Indeed a useful document. Have you checked the above link for SAP PS tables?

Thanks

Regards

Srinivasan Desingh

Former Member
0 Kudos

Thanks Sunil, Useful document.

sunil_yadav2
Active Contributor
0 Kudos

Hi Srinivasan,

Yes i have checked this document also and this is very good document.

i thought that every person has different way of seeing or comfort level. so i have created the same. In real time some consultant use SE11 but some SE16 so its totally depend on individual comfort level.

as far as my concern, i am able to understand both documents and i usually refer both documents as well.

Thanks for your support!! and expecting more informative documents so we can learn more.

thanks & regards

Sunil

sunil_yadav2
Active Contributor
0 Kudos

Thanks Sandeep :smile:

raghubirsap
Explorer
0 Kudos
Good Job Sunil Sir

Really appreciated this help & Support.

Keep on updating the Blog with useful content related with sap.

 
sunil_yadav2
Active Contributor
Thanks Raghubir.
Former Member
thanks so much

 
sunil_yadav2
Active Contributor
0 Kudos
Welcome Omar 🙂
former_member391408
Discoverer
0 Kudos

Thanks for the steps explanation.

SAP Project System (PS) SAP Project System (PS) is a project management software tool that integrates with other components of the SAP Enterprise Resource Planning (SAP ERP) system.

 

sunil_yadav2
Active Contributor
0 Kudos
Thanks Nikki 🙂
ananias
Explorer
0 Kudos

Guys I have Challenge pulling the actual costs.

project_actual_costs comes as 0.00

 

  DATA:
it_posid TYPE TABLE OF prps-posid WITH HEADER LINE,
it_prps TYPE TABLE OF prps WITH HEADER LINE,
it_aufk TYPE TABLE OF aufk-aufnr WITH HEADER LINE,
it_afko TYPE TABLE OF afko-aufpl WITH HEADER LINE,
it_afvc TYPE TABLE OF afvc-objnr WITH HEADER LINE,
it_rpsco TYPE TABLE OF rpsco WITH HEADER LINE
.

DATA: total TYPE coss-wog001,
actual_cost TYPE bp_wpl,
planned_cost TYPE bp_wpl.
" projn1 TYPE prps-psphi VALUE '00000174'.

RANGES:
lr_onjnr FOR prps-objnr,
lr_posid FOR prps-posid,
lr_aufk_aufnr FOR aufk-aufnr,
lr_afko_aufpl FOR afko-aufpl,
lr_afvc_objnr FOR afvc-objnr,
lr_rpsco_objnr FOR rpsco-objnr.

lr_posid-sign = 'I'.
lr_posid-option = 'EQ'.
SELECT posid INTO it_posid FROM prps WHERE psphi = projnr.
lr_posid-low = it_posid.
APPEND lr_posid.
ENDSELECT.

lr_aufk_aufnr-sign = 'I'.
lr_aufk_aufnr-option = 'EQ'.
SELECT aufnr FROM aufk INTO it_aufk WHERE pspel IN lr_posid[].
lr_aufk_aufnr-low = it_aufk.
APPEND lr_aufk_aufnr.
ENDSELECT.

lr_afko_aufpl-sign = 'I'.
lr_afko_aufpl-option = 'EQ'.
SELECT aufpl FROM afko INTO it_afko WHERE aufnr IN lr_aufk_aufnr[].
lr_afko_aufpl-low = it_afko.
APPEND lr_afko_aufpl.
ENDSELECT.

lr_afvc_objnr-sign = 'I'.
lr_afvc_objnr-option = 'EQ'.
SELECT objnr FROM afvc INTO it_afvc WHERE aufpl IN lr_afko_aufpl[].
lr_afvc_objnr-low = it_afvc.
APPEND lr_afvc_objnr.
ENDSELECT.

SELECT * FROM rpsco INTO it_rpsco WHERE objnr IN lr_afvc_objnr AND wrttp = 4.
project_actual_cost = project_actual_cost + it_rpsco-wlp00 + it_rpsco-wlp01 + it_rpsco-wlp02 + it_rpsco-wlp03 +
it_rpsco-wlp04 + it_rpsco-wlp05 + it_rpsco-wlp06 + it_rpsco-wlp07 +
it_rpsco-wlp08 + it_rpsco-wlp09 + it_rpsco-wlp10 + it_rpsco-wlp11 +
it_rpsco-wlp12 ."+ it_rpsco-wlp13 + it_rpsco-wlp14 + it_rpsco-wlp15 +
"it_rpsco-wlp16.

ENDSELECT.

 

hthakar
Member
0 Kudos
Please add the table for finding the Relationships between Activities in Standard & Operational