on 04-20-2015 9:45 AM
Dear All,
I have observed for few clients, the time recording in CAT2 is done against the receiver/sender cost center. For others, the time is recorded against a network ID. What is the difference between these two? When do we need a network ID and when do we go for cost centers?
Does this selection affect the time postings?
Thanks
Hi Abdul ,
Say for example - Billable (T& M Process ) and non billable hours :
Billable hours : This process is integrated with other logistics like Sales & Distribution, Project system ,Human resource and Finance .
Sales order is created in SD , once it is created WBS generated in order itself . PS team will assign the responsible manager and resources , based on that employee is recorded the billable hours thur CAT2.
Project Manager should approve the time entries in CATS_APPR and HR admini run the report CAT7 (transfer to controlling).
Order creation - VA01 and WBS assignment CJ01N
Sender cost center is mapped in Infotype 315.
Sender cost center , Activity type ,WBS and A/A , Hours are mandatory in CAT2.
Non billable hours : Reporting manager approves the leave request / non billalbe hours (Bench hours / Holidays...) For this we have to maintain the emp and manager relations in HRP1001 or PO13.
Should be maintain infotype 105 and subtypes 0001 and 0010.
Regarding Network ID : Please check the below link:
What is a Network? - Project System (PS) - SAP Library
Regards
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
9 | |
8 | |
7 | |
7 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.