on 05-29-2023 1:34 PM
Related to Production Version, I did not find any note which refers the consistency check validation after to execute the program CS_BOM_PRODVER_MIGRATION02 for phantom and subcontracting materials in S/4.
Sounds good. Thanks for sharing!
Now, my concern is related to BOM date valid from. The Production Version is considering valid from of date that the program was executed, instead of BOM valid from. This issue impact the requirements created in the past