cancel
Showing results for 
Search instead for 
Did you mean: 

KE28 Variants

90070279
Participant
0 Kudos

We have 31 KE28 variants and someone has to update the period values each month. We have a custom variable variant for dynamic date selection with the proper format but I do not see how to link the variable variant to the KE28 period selection parameter. If possible, I would like KE28 Actual and Reference periods to both default to the prior period.

So my question is whether we can do one of the following:

1) Default in previous period whenever KE28 is run.

OR

2) Find a way to save a month/year value in the From Period fields that are dynamic as part of the report variant.

Any help is appreciated.

Thanks,

Tim

View Entire Topic
former_member188826
Active Contributor
0 Kudos

You may want to copy the standard program RKEBPBATCHGITD to a customized and arrange to have a developer to provide the desired values for those fields.