on 04-01-2008 2:29 PM
We have 31 KE28 variants and someone has to update the period values each month. We have a custom variable variant for dynamic date selection with the proper format but I do not see how to link the variable variant to the KE28 period selection parameter. If possible, I would like KE28 Actual and Reference periods to both default to the prior period.
So my question is whether we can do one of the following:
1) Default in previous period whenever KE28 is run.
OR
2) Find a way to save a month/year value in the From Period fields that are dynamic as part of the report variant.
Any help is appreciated.
Thanks,
Tim
You may want to copy the standard program RKEBPBATCHGITD to a customized and arrange to have a developer to provide the desired values for those fields.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
78 | |
8 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.