MRP created multiple PR For Material Which Has Existing POs Available

ssaher412
Explorer
0 Kudos

Hi Experts,

We have one material with MRP type as VB, reorder point is 1 and minimum lot size is 2. After running the MRP PR got created for 2 qty. We have converted this PR to PO. Next day when we again run the MRP it again created PR for 2 qty. As the requirement from first PO got fulfill then why MRP again created the PR. Request your help on priority.

 

@SAPSupport @Caetano 

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hello
View Entire Topic
arjuna_bandara
Active Participant
0 Kudos

Hi,

Does this PO also appears in the stock requirement list (MD04)?, if not check if the delivery completed indicator has been set at the PO line item delivery tab (regarded as closed)

 

ssaher412
Explorer
0 Kudos
Hi Arjuna, the PO's are appearing in the MD04 screen. This PO is still open.