Dear Experts,

We have problem in the Actual cost splitting form KSS2 . We have Posted the SKF from the T code KSU5 and value has been distributed from service cost center to the Production cost centers S_ALR_87013611 -

But in the KSS2 system is showing the allocation amount distributing for all activity types.

Example:- We did KSU5 for Permanent labour The amount of Permanent labour should show in the Permanent labour column along with actual cost But the system is dividing for all please help

Regards

Nissa

0 Kudos

Dear Experts

As screen shared equilance number we maintained as 1.

If we changed equilance number what would be impact and how equilance number works

Lot of research I did but no luck

0 Kudos

Dear experts

Please help on this

Regarda

Nissa

hohoman
Active Participant
0 Kudos

Could you pls add information about the Splitting structure and Splitting rules you're using?

View Entire Topic
vvf_coreteam
Explorer
0 Kudos

Dear Homman,

Thanks for your reply

We are using Rule 1 (Split According to Activity QT) against the Acclivity type.

& also confirm us why the system is allocating the cost to all activity types

as per my understanding if the Target cost not maintain for the particular cost element

system will take value from eqvilance and divide the value from above activity cost element

is my understanding correct please correct me if i am wrong.

Regards

Nissa

elforse
Explorer
0 Kudos
Dear vvf_coreteam
elforse
Explorer
0 Kudos
Dear vvf_coreteam is this problem is solved becouse i have same problem here