Hi Folks,

We had a contract with the customer for a project and the same is the milestone-based project. The billing pattern is mentioned below

  • Milestone -1 – end of 4th week
  • Milestone – 2 – end of 8th week
  • Milestone – 3 – end of 12th week
  • Final payment – 4 Post project closure.

The above project is a subcontract to a third-party vendor same billing pattern i.e. milestones and 6 resources are working on this project. The vendor will raise the invoice on the completion of each milestone.

Considering the above transaction we wanted the purchase order creation of the milestone-based project.

What is the best way to do this process?

View Entire Topic
Gabor_Kovacs
Product and Topic Expert
Product and Topic Expert
0 Kudos

You can setup Periodic Invoicing Plan - milestone-based PO is not available at this moment.

See the online help for details: Creating an Invoicing Plan - SAP Help Portal