Dear team, as you are aware, we run mrp and then cm25 capacity levelling seperately in ecc. Please advise whether we can do material availablity planning and capacity levelling at a time in s4hana without using ppds system? Please advise what steps we need to follow both in s4hana and in ppds systems. Appreciated.
Hi,
As you are aware, that in S/4HANA without (ePP/DS) you only have the MRP engine which is not a constrained planning engine. Due to which you would need to execute two different steps to perform materials planning followed by capacity planning separately. Ofcourse from a scenario planning perspective (i.e. which is suppose to replace LTP) you can explore the options of pMRP (predictive Material and Resource planning) where you can execute both plans through this process.
I hope this answers your question.
Regards
Sasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.