Hi Team,

We have the following scenario

Sales order is placed in a DC plant which is produced in a MP plant and transferred to the DC. The sales order in DC creates a Stock transfer requisition in the MP with reference to the sales order. The MRP run creates a planned order without reference to the sales order whereby delivery for the sto is not created . Is there a way in which the planned order created in the MP can refer to the sales order in DC whereby the delivery can be created against the STO to transfer the goods to the DC

View Entire Topic
Amit_SAP
Active Contributor
0 Kudos
nevin_philip
Participant
0 Kudos

Hi Amit,

Thanks for your response. Our scenario is more of the MTO scenario. Let me put this in more detail

Plant X is a DC and Plant Y is a MP. Order for Material A is received in plant X which creates a STR to plant Y with account assignment category E and the sales order. I want to create a planned order when i run MRP in plant Y to receive the stock against the sales order so that the GI from the delivery in the STO can be done against the sales order stock. Any suggestions on how this can be done?