Why does MRP Live on HANA not support parameter effectivity?

eduardo_vargas
Explorer

Based on SAP Note 1914010 and 2986887 MRP Live on HANA does not support parameter effectivity, I would like to more information about it, because SAP does not provide any further details in this notes.

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Eduardo

MRP Live can plan materials with parameter effectivity, as of SAP Note 2986887 MRP live: dispatch parameter effectivity materials to classic MRP

The only drawback is that materials with parameter effectivity will be planned in ABAP, instead of being planned in HANA.

Best regards,
Caetano