Hi,

Thanks for the additional information. From what I'm seeing and from what you have said it seems to me the system has automatically scheduled the Maintenance Plan. Do you have a batch job running for IP30 that the parameters would include this plan? The standard process of IP30 is to schedule the plans then call the WO so this could be what has happened.

To fix you will have to restart the Plan and 'Do Not Execute' the WO called.