simplification of S/4 HANA migerationin SAP Note 2268044 - S4TWL - PP-MRP - Subcontracting

Former Member
0 Kudos

for simplification of S/4 HANA migerationin SAP Note 2268044 - S4TWL - PP-MRP - Subcontracting

i want to ask aquestion about is the meaning of (3.0 logic - 4.0 logic - 4.5 logic ) in subcontracting process ?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Nassar

The 3.0 logic is the subcontracting logic available in release 3.0, where there was no separation between the plant stock and the stock provided to the vendor, from a planning perspective.

The 4.0 logic is the default logic for subcontracting in the current ECC releases, where you see the stock provided to the vendor in a separate stock segment in transaction MD04.

Regards,

Caetano

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Caetano,

What is the exact simplification/Innovation observed in case of Subcontracting, consignment.,scheduling,contract in case of S4 HANA EM when compared to ECC.

Please advise.,

Regards,

G.V.Shivakkumar