Why does MRP Live on HANA not support parameter effectivity?

eduardo_vargas
Explorer

Based on SAP Note 1914010 and 2986887 MRP Live on HANA does not support parameter effectivity, I would like to more information about it, because SAP does not provide any further details in this notes.

Accepted Solutions (0)

Answers (2)

Answers (2)

EmanuelGraves
Explorer

The limitation mentioned in the SAP notes indicates that MRP Live on HANA does not fully support parameter effectivity functionality. This means that certain features or capabilities related to parameter effectivity may not work as expected or may be unavailable when using MRP Live on HANA. For organizations that heavily rely on parameter effectivity for managing product variations and configurations, this limitation may impact their ability to accurately plan and procure materials using MRP Live on HANA. It could result in challenges related to planning accuracy, inventory management, and production scheduling.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Eduardo

MRP Live can plan materials with parameter effectivity, as of SAP Note 2986887 MRP live: dispatch parameter effectivity materials to classic MRP

The only drawback is that materials with parameter effectivity will be planned in ABAP, instead of being planned in HANA.

Best regards,
Caetano