03-31-2024 12:39 PM - edited 03-31-2024 3:02 PM
Hello everyone,
In SAP Project System, in transaction CJ20N, when I assign a material component to an internal activity and choose my material, then I select "L" stock item for this material and I choose the following procurement type to generate a PR: PReq + Reservation for WBS Element. Afterwards, I enter the requirement quantity for this material component and then I hit enter on the keyboard to finalize the creation of this material component. I realize that the GL account assigned to this material automatically changes, from 3090300 (GBB-->VBR) to 1211000 (BSX) and an error is shown which says "GL account 1211000 is invalid". I can't save the progress for my project because when I do there is error in calculating costs since the system saw an error in this material component. What could be the cause of that?
Note: My project stock is maintained as valuated stock in the project profile configuration.
Thank you
With Valuated Project Stock at GR of the PO it will post to a Balance Sheet Inventory Account (they typically start with a 1). So that looks correct. What error message (and error message number) are you getting?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sir,
The error description is as follows:
Message No. CO860
The G/L account that you have entered is invalid.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.