on 09-29-2022 11:14 AM
Hello Team,
We are not able to run the MRP in S/4HANA because of some constraints like multiple BOM but looking to implement IBP for demand planning now. So, what should we do? We should first rectify the issues and run the MRP in S/SHANA or IBP will take care it. Can we run MRP in IBP?
Thank You
MRP in SAP IBP is possible in IBP S&OP and Response & Supply module in the form of Heuristics and/or Optimiser engine`. MRP is not a capability of IBP Demand component that focuses on generating demand forecast by statistical means from history data and further enhanced by planners.
BTW if you are not able to run MRP in S/4HANA due to multiple BOMs (not sure about the scenario) then it will not get solved in SAP IBP. IBP is planning application that has its own master data which is integrated with S/4HANA so that planning and execution are aligned.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.