Hello,

We are calculating cost in Freight Orders and use cost distribution to distribute the costs.
The Freight Order exist of multiple part loads with different source and destination locations.

In case there existing costs for waiting hours and we allocate costs for this waiting hrs, costs need to be distributed to the right document. Costs for waiting hrs is relevant for documents with the location where waiting hrs exist.

Is there a way to distribute costs to a specific document? Currently, with standard cost distribution method, costs will be divided to all documents instead to the relevant document(s).

View Entire Topic
01a02b03c
Active Participant
0 Kudos

Hi Leandro,

I have found it in the meantime. In TM it is possible to add a charge line with logistical reference. This works when charges will be calculated at STAGE level. The part of Cost Distribution isn't correctly at this moment. I think we can use your information regarding the Cost Distribution method.

Thanks for your help.

Kind Regards,

René