on 05-18-2017 2:08 PM
Dear Experts,
We have a requirement to set Frozen Horizon flexibly based on Product Class. As such,
1. For Product Class A, forecast cannot be entered for current week and next week -> any updates can be done from Week 3 onward (considering current week as Week 1)
2. For Product Class B, forecast cannot be entered for current week and next 3 week -> any updates has to be entered from Week 5 onward
and so on.
We have written a macro to identify the time period as frozen or editable locally in excel worksheet, but the refresh time is significantly higher -> due to macro reading each cell one by one and locking.
As we are only using S&OP module for Sales Forecasting modelling, we are not configuring Product-Location based Frozen Horizon, and use Heuristics/Optimizer to prevent Supply Plan change due to changes in Sales Forecast entered in the 'frozen horizon' .
Please guide, if there is any other elegant methods that can be used fo rthis.
Regards,
Shivpriye
Hi Peter,
Thanks for sharing the Influence link, in that way other partners and consultant can Up Vote this enhancement as well.
Best,
Ivan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.