When a planning run takes place in PPDS and orders (PO and Preqs) are created/changed in a planning run. If you do not want to transfer changes from APO to ECC without deactivating CIF IM. How can we achieve it?
1. Option would to run PP/DS in a planning version != active planning version.
2. Option would to filter out the changes for the specific plant, planner etc. in the CIF and delete them. Set the CIF transfer to collect changes /SAPAPO/C4 (make sure to also select background user & the user for which you don't want to transfert results) then in SAPAPO/C5 delete the objects (only high level - think about the details like including background user etc.)
With this you have the option do only transfer results for select plants, material etc. etc. or no at all - but you don't have to turn off this CIF.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.