Hi team

i was migrating AR and AP using LTMC and thought of cancelling it. Now the problem is that it has been 4 hours and cancellation of migration object is still running.

I am not able to start new LTMC migration due to this

Javier-Martin
Product and Topic Expert
Product and Topic Expert
0 Kudos
Wrong tag for this question, please modify the tag to allow the right experts to answer it. Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

NTeunckens
Active Contributor
0 Kudos

Have you seen the following post : Solved: Keep running Data Migration Job - SAP Community
There are a number of SAP-Notes, explaning how "LTMC" can have issues in long runtimes and / or being stuck on 'early steps' such as the data validation-step.
The post reveals a way to check if there's a job pending and terminate it.
Further, it offers useful SAP-Notes on the use and side-effects when using "LTMC" ...