on 07-11-2016 2:46 PM
Hi,
does anyone have an idea how a customer can schedule the "Filling OLAP Cache" task as a background job without the Broadcaster? (Broadcaster cannot be used due to missing Java stack at the moment. Installing the Java stack would be the easisest I assume but this is not possible at the moment)
Thanks,
Deniz
Hi Deniz,
Please remember that the OLAP Cache will will filled when ever you execute the query.
Consider RSRT to schedule your query to be execute daily.
See
Transaction RSRT: Query Monitor - SAP NetWeaver Business Warehouse - SCN Wiki
Generate Report and Generation Log
Do you have BusinessObjects?
Consider creating a Webi report with query as source and use the BOBJ scheduler.
Please don't forget to record your final solution and to mark the question as answered.
Good luck,
John Hawk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deniz,
Try using a process chain. I don't have access to a BW system currently, but I think there is a variant for filling the cache. I don't recall if it requires the java stack or not.
Please don't forget to record your final solution and to mark the question as answered.
Good luck,
John Hawk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Deniz,
Please could you tell me if you found some workaround, I developed a Fiori app connected to BW queries, but I would like to fill the cache before users use the app, but in this case I don't find Fill Olap Cache distribution Type in my options so I suppose that my Bex Broadcaster version is 3.x.
Thanks in advanced.
Regards.
Jhon Jairo.