Permit to Work process is a critical and mandatory process for asset intensive industry such as Oil and Gas, Utilities, Chemicals etc. The process ensures safety of maintenance workers while performing tasks in hazardous environment.
In the SAP S/4H...
My customer has a requirement to integrate SAP system (module PM, PS) with 3rd party systems such as MS Projects or Oracle Primavera etc. The connector used for such integration is SAP EPC 3.0. However, as per the installation guide, the EPC 3.0 is o...
Permit to Work process is a critical and mandatory process for asset intensive industry such as Oil and Gas, Utilities, Chemicals etc. The process ensures safety of maintenance workers while performing tasks in hazardous environment.
In the SAP S/4H...
Permit to Work process is a critical and mandatory process for asset intensive industry such as Oil and Gas, Utilities, Chemicals etc. The process ensures safety of maintenance workers while performing tasks in hazardous environment.
In the SAP S/4H...
Hi,I have the following scenario:I need to attach a PDF document to a PM order. This can be achieved using the standard feature of attaching documents to SAP Objects. The requirement is to open the same attached document and update it by entering som...
Hello @pardhreddyc The permit management in PTW(the new solution with Fiori) or the classical one with WCM caters to the overall permit solution (creation, preparation, implementing safety controls, approval, print out, handout and closure). This is ...
Hi Szabina,
What you are calling fiori is actually web dynpro ABAP (option 2 in the blog).
View profiles only work for SAP GUI (option 1). If you want to change the layout of WDA screen, you need to do it through the floor plan manager framework...
Hi Dirk,
Thanks for the feedback. As of now, list features available with SAP GUI and not webdynpro. THe roadmap is under-progress. Will share updates once it is available.
Regards,
Arvind